|
Smith Pachter McWhorter PLC
Government Contracts Update
Vol. III, No. 1 March, 2007
By Stephen D. Knight
Smith Pachter McWhorter constantly tracks current events, issues, and trends in Government Contracts to keep clients on the cutting edge of legal and policy developments. This e-letter highlights the most important issues, and the attached index provides weblinks to the source documents of these and many more developments.
I. Proposed FAR Poses Substantial Issues for Compliance
While the newspaper headlines have highlighted major Congressional efforts to roll back changes made 15 years ago under Acquisition Reform, the government contractor community should not lose sight of a proposed Federal Acquisition Regulation (FAR), “Contractor Code of Ethics and Business Conduct.” 72 Fed. Reg. 7588 (February 16, 2007).
That proposed regulation would impose requirements for contractors to establish a code of ethics and business conduct, implement a compliance training program, and establish internal control systems incorporating specific duties. The proposed rule would also impose significant reporting and cooperation obligations on contractors.
The proposed rule is similar to the regulation contained in DFARS Subpart 203.70, but, unlike the DFARS provision, the proposed rule would be mandatory, except for commercial item contracts and contracts performed outside the United States. The proposed rule would impose the most stringent requirements on contracts awarded in excess of $5 million with a performance period of 120 days or more. In that instance, the proposed contract clause would require the contractor to have a written code of ethics and business conduct within 30 days after award, and within 90 days after award to establish (a) an employee ethics and training program; and (b) an internal control system. “Such program and system shall be suitable to the size of the company and its involvement in Government contracting.”
The proposed rule would mandate that the internal control system:
(i) facilitate timely discovery and disclosure of improper conduct in connection with Government contracts; and
(ii) ensure corrective measures are promptly instituted and carried out.
By way of example, the proposed rule states that a contractor’s internal control system should provide for:
(i) periodic reviews of company business practices, procedures, policies, and internal controls for compliance with the contractor’s code of ethics and business conduct and the special requirements of Government contracting;
(ii) an internal reporting mechanism, such as a hotline, by which employees may report suspected instances of improper conduct, and instructions that encourage employees to make such reports;
(iii) internal and/or external audits, as appropriate;
(iv) disciplinary action for improper conduct;
(v) timely reporting to appropriate Government officials of any suspected violations of law in connection with Government contracts or any other irregularities in connection with such contracts; and
(vi) full cooperation with any Government agencies responsible for either investigation or corrective actions.
The proposed contract clause would also require prominent posting of a fraud hotline poster in common areas and on the company website. Remedies for violation of these requirements would include withholding of contract payments or loss of award fee. The proposed clause would be a mandatory subcontract flowdown clause.
The impact of such a regulation would be substantial. While major companies within the defense industry have implemented codes of ethics and business conduct, and compliance programs, many other, smaller companies within and outside the defense industry have not, or have not implemented programs to meet the above criteria. The threshold for imposing this kind of stringent requirement is, by any measure, very low – a single contract or subcontract award in excess of $5 million with a performance period of at least 120 days.
The concept of compliance is a difficult one with which to argue, but the proposed rule suggests an unprecedented level of government audit, investigation, reporting, and oversight. For example, what does the clause mean by “special requirements of Government contracting”? Whom will the government identify to ascertain whether contractors comply with the proposed clause and the identified internal control system criteria? DCAA? The agency Inspector General? What level of audit access will the government demand to determine compliance with the proposed clause? Will the government be the final authority on the adequacy of the contractor’s “periodic reviews,” the treatment of hotline reports, the conduct of internal and external audits, and the appropriateness of disciplinary action taken by the company for improper conduct?
The additional requirement of contractor “timely reporting to appropriate Government officials any suspected violations” or “any other irregularities in connection with” government contracts presents serious issues of interpretation. How much information, and what quality, will require a contractor to make a report? Will a contractor be able to make a factual investigation to determine whether to file a report, or must a contractor make a report based on unsubstantiated hearsay or, worse, mere suspicion?
The proposed clause’s requirement that the contractor provide “full cooperation with any Government agencies responsible for either investigation or corrective actions” also presents serious issues. What does “full cooperation” mean? Is this a requirement for employee interviews? If so, what is the contractor’s duty with respect to the rights of its employees? Will an employee’s refusal to submit to an interview implicate a breach of the clause and therefore the government’s right to withhold payments? Does “full cooperation” require waiver of attorney-client privilege?
No one would argue that compliance in government contracts is unimportant. But the proposed FAR rule is a “meat cleaver” approach to compliance, and will lead to significant increased costs for contractors and subcontractors to do business with the government.
II. Recent Decisions Demonstrate Aggressive DOJ Tactics, Contractor Burden to Avoid Fraud and Forfeiture
Two cases appear to have attracted a lot of attention recently, and have led some commentators to opine that the federal government is taking a "new tack" in its treatment of contractors. While the results in the two cases are dramatic, the substantive decisions should come as no surprise. The lesson of Daewoo Engineering and Construction Co. v. United States, 73 Fed. Cl. 547 (2006), is: contractors may not use unsubstantiated claims to leverage their negotiating position with the government under the Contract Disputes Act. The lesson of AMEC Construction Management, Inc. v. United States, 2007 US Claims LEXIS 10 (Jan. 26, 2007) is: double-billing and subcontractor kickbacks will not be tolerated in government contracts. Such actions have severe consequences.
The Daewoo decision reads like a lesson in how not to assemble or litigate a claim. The contract required construction of a 53-mile, two-lane road on a tropical island within the Republic of Palau. Daewoo's initial bid was $73 million, less than the government's estimate, and $26 million less than the next bidder. The government warned the contractor that the bid seemed low and permitted an increase in price to $88 million. After encountering performance difficulties, Daewoo submitted a $64 million claim, certified under the Contract Disputes Act, essentially premised on the contract's Weather Clause, and asserted government liability for defective specifications, superior knowledge, and impossibility. Of the $64 million claimed, $13 million were described as "incurred damages" and $50 million were projected and not yet incurred.
The central problem with Daewoo's claim was that the contractor filed it to get the government to "pay attention" to, and approve, Daewoo's preferred method of compaction. The court stated:
"Daewoo's project manager testified that plaintiff filed at least $50 million of its certified claim as a negotiating ploy; Daewoo's counsel essentially confirmed it: 'Daewoo's suggestion that the Government expedite a previously approved and validated alternative embankment placement method is a reasonable request that served the projects best interests and, therefore, is grossly mischaracterized as a ploy.' Unfortunately, Daewoo's 'reasonable request' or 'suggestion' that the Government 'expedite' approval of the cheaper compaction method took the form of a certified claim."
The court discussed at length the inconsistencies in testimony from Daewoo's witnesses. For example, the project manager testified that he expected the government to pay the entire $64 million and then, later that same day, testified that the claim was only for $13 million. The court noted that Daewoo's management "could not or would not explain how they calculated the bid." The court also noted that Daewoo would not present its own weather calculations in discovery or during trial. The court characterized the testimony of Daewoo's experts as "obtuse." The experts, according to the court, "emphasized that they had not read the certified claim," and "they wished to distance themselves from any numbers or supporting data that had been a part of that claim." Daewoo's experts testified to an amount $22 million less than the certified claim.
At the end of Daewoo's case, the government moved to amend its answer to add fraud counterclaims. The court granted the motion, and the government counterclaimed under the Contract Disputes Act, 41 USC § 604, the Forfeiture Statute, 28 USC § 2514, and the civil False Claims Act, 31 USC § 3729. The court found that the government was not liable for the $13 million of costs incurred, and that the remaining $50 million had been submitted as a negotiating ploy. The court determined that the entire claim was an attempt to defraud the government, and found Daewoo liable to the government under the CDA "for an amount equal to such unsupported part of the claim" -- $50.6 million.
The AMEC case involved payment and performance bond costs on several federal construction contracts. The government moved for summary judgment on its counterclaims under the Anti-Kickback Act, 41 USC §§ 51-58, and the civil False Claims Act, 31 USC § 3729. The facts showed that the contractor's parent company had established a "rebate" program with its bond brokers, whereby the parent company received an amount equal to the actual bond cost. The court found that this practice violated the Anti-Kickback Act. The court also granted summary judgment to the government based on the civil FCA because the contractor had billed the bond costs, including the "rebate," as part of its progress payment requests, thereby inflating those progress payment requests. Finally, the court determined that AMEC's claims for equitable adjustment filed under the contracts at issue were forfeit under the Forfeiture Statute.
Neither Daewoo nor AMEC should come as a surprise. Both cases involved claims that the court determined were either fraudulent or tainted by fraud. In Daewoo, the court found that $50 million of the contractor's claim was unsupported and filed as a negotiating ploy, a tactic the CDA was designed to stop. In AMEC, the "rebate" constituted a kickback and also led to inflated progress payment requests, thereby tainting the contractor's other claims for equitable adjustment. The message from the US Court of Federal Claims is clear: tactics such as these are impermissible and will have severe consequences.
While the statutes at issue in these two cases are not new, recent experience indicates that government counsel, from both the Department of Justice and agencies, are asserting fraud counterclaims and arguments on a more frequent basis to counter contractor claims. The most effective way to oppose these government positions is to make certain that contract claims are fully supported with adequate facts, and that the company implement a compliance program to ensure that only appropriate costs are bid, incurred, charged to the contract, and billed to the government.
LINKS TO RECENT DEVELOPMENTS IN
GOVERNMENT CONTRACTS
I. LEGISLATION
- S. 226, “To direct the Inspector General of the Department of Justice to submit semiannual reports regarding settlements relating to false claims and fraud against the Federal Government” (January 9, 2007)
- S. 119/H.R. 400, “War Profiteering Prevention Act of 2007” (January 4, 2007)
- H.R. 528, “Iraq Contracting Fraud Review Act of 2007” (January 17, 2007)
- H.R. 369, “Transparency and Accountability in Security Contracting Act of 2007” (January 10, 2007)
- H.R. 180, “Darfur Accountability and Divestment Act of 2007” (January 4, 2007)
- H.R. 46, “Small business Tax Fairness and Simplification Act of 2007” (January 4, 2007)
- H.R. 2, “An Act to amend the Fair Labor Standards Act of 1938”, Sec. 249
- H.Res. 97, “Providing for Operation Iraqi Freedom cost accountability” (January 24, 2007)
- David M. Walker, “Suggested Areas for Oversight for the 110th Congress” (November 17, 2006)
- Henry A. Waxman, correspondence re testimony on Iraq reconstruction at February 6, 2007, hearing (January 17, 2007)
- Government Withholding Relief Coalition, letter to Rep. Greg Walden (January 16, 2007)
II. REGULATIONS & POLICIES
- Notice, “Renegotiation Board Interest Rate; Prompt Interest Rate; Contract Disputes Act,” 71 Fed. Reg. 78513 (December 29, 2006)
- Proposed Rule, “FAR: Performance-based Payments,” 71 Fed. Reg. 75186 (December 14, 2006)
- Final Rule, “FAC 2005-15,” 71 Fed. Reg. 74656 (December 12, 2006)
- Interim Rule, “DFARS: Emergency Acquisitions,” 72 Fed. Reg. 2631 (January 22, 2007)
- Final Rule, “DFARS: Notification Requirements for Critical Safety Items,” 72 Fed. Reg. 2633 (January 22, 2007)
- Notice, “DFARS: Information Collection Requirement,” 72 Fed. Reg. 2663 (January 22, 2007)
- Interim Rule, “DFARS: Labor Reimbursement on DOD Non-Commercial Time-and-Materials and Labor-Hour Contracts,” 71 Fed. Reg. 74469 (December 12, 2006)
- Final Rule, “DFARS: Levy on Payments to Contractors,” 71 Fed. Reg. 69489 (December 1, 2006)
- Final Rule, “DFARS: Contract Pricing and Cost Accounting Standards,” 71 Fed. Reg. 69492 (December 1, 2006)
- Proposed Rule, “DFARS: Contracting Methods and Contract Type,” 71 Fed. Reg. 65768 (November 9, 2006)
- Advanced Notice of Proposed Rulemaking, “Key Subcontractor Consent Requirements,” 72 Fed. Reg. 3778 (January 26, 2007)
- OUSD Memorandum, “Impact of the Pension Protection Act of 2006 on Forward Pricing” (December 22, 2006)
- OUSD Memorandum, “Class Deviation – Restriction on Procurement of Specialty Metals” (December 6, 2006)
- Robert T. Marlow letter to Laurieann Duarte, “FAR Case 2005-027 (FAR Part 30 – CAS Administration)” (December 4, 2006)
- DCAA Memorandum, “Audit Guidance on Performing Cost Accounting Standards (CAS) 410 Compliance Audits at Contractor Offsite Locations” (October 17, 2006)
- DCAA Memorandum, “Transmittal of Director, Defense Procurement and Acquisition Policy (DPAP) Interim Guidance on the Impact of the Pension Protection Act of 2006 on Forward Pricing” (October 12, 2006)
III. CASES
- The Long Island Savings Bank v. United States,
No. 2006-5029 (Fed. Cir. February 1, 2007) (Winstar-related case; government need not prove reliance or injury to prove forfeiture under 28 U.S.C. § 2514)
- Schleicher Community Corrections Center, Inc. v. Gonzales, No. 2006-1215 (Fed. Cir. January 8, 2007) (“contractor can recovery interest [under the CDA] only on amounts it actually paid”)
- Morse Diesel International, Inc. v. United States, No. 99-279C (COFC January 27, 2007) (government entitled to summary judgment under AKA and FCA; contractor forfeited claims exceeding $53 million under 28 U.S.C. § 2514)
- The Boeing Co. v. United States, No. 91-1362C (COFC January 17, 2007) (government breached contract by causing award fee to be mandated by DOE headquarters rather than determined by person named in contract)
- Alliant Techsystem, Inc. v. United States, No. 01-20C (COFC January 4, 2007) (contractor’s claim for postretirement benefits barred by release in settlement agreement)
- Pilley v. United States, No. 05-382C (November 30, 2006) (patent infringement suit fails due to FAR 52.227-11 paid-up, non-exclusive licenses to government)
- Southwest Marine, Inc. v. United States, No. 05-CV-1189 WQH (RBB) (S.D. Calif. December 15, 2006) (affirms ASBCA decision to disallow attorney fees incurred in defense of Clean Water Act litigation, under FAR 31.204 “similar or related” provision)
- Lockheed Martin Aircraft Center, ASBCA No. 55164 (January 11, 2007) (denying government motion to dismiss based on “sum certain”)
- Paul J. McNulty, U.S. Department of Justice Memorandum, “Principles of Federal Prosecution of Business Organizations”
IV. REPORTS
The
information in this newsletter is not, nor is it intended
to be, legal advice. You should consult an attorney for individual
advice regarding your own situation |